After applying for the program, you will need to schedule an appointment to submit complete application packet. From there the following items will occur within the timeframes below:
Packet Review and Processing Complete Application
Within 30 days staff will review packet and will process complete application.
Schedule Property Inspection
Within 7 business days of application approval, staff will schedule property inspection.
Determination of Scope
Within 5 business days of the completed property inspection, a scope of work will be determined for the project.
Committee Approval
Within 14 business days of determining the scope, the proposed project will be presented to committee for approval;
Walk Through
Within 10 business days of committee approval, a contractor walk through will be scheduled.
Selection of the Contractor for Project
Within 10 business days of the walk through, a contractor will be selected based upon bid results, and loan documents signed.
Notice to Proceed
Within 10 business days of the contractor selection, the documents will be executed and recorded, and a Notice to Proceed issued.
Work Completed
Within 30 to 45 days of receiving the Notice to Proceed, work will begin and be substantially completed.
Final Inspection
Within 5 business days of completion, there will be a final Inspection, Notice of Completion, Warranty Information and closeout letter issued.